Reinforcement and Retrofitting of Footings at Caterpillar's Reynosa Facility
November 5 2001
The steel frame originally built to support an overhead crane is being reinforced and retrofitted to sustain walls and roof that will cover Caterpillar's outdoor production area.
       
Reinforcement and Retrofitting of Steel Frame
November 12 2001
CINL is working closely with Caterpillar so as not impede on the Caterpillar's production line, which has been operational for the most part of the construction process.
       
Reinforcement and Retrofitting of Steel Frame
November 19 2001
Photograph shows how the existing crane supports were seamlessly retrofitted to accommodate the reinforced frame elements that will sustain the wall and roof at Caterpillar's Reynosa production facility.
       
Installation of  Steel frame Extensions at Caterpillar's Reynosa Facility

November 26 2001
CINL began work on the placement of extensions to the frame of Caterpillar's Reynosa facility; these extensions will support the roof and walls that will enclose the crane runway, which is now an open-air production area.