  June 1999 PROJECT NEWS  
Previous Month

Next Month
Lucent Technologies in Matamoros, Tam.
June 7 1999
Expansion to Lucent Technologies facility in Matamoros was completed and delivered. This project required relocating A/C and cooling equipment used by original building, this was done with no interruption to the production lines on the original building.
       
Entec / Mitsubishi Aerial Photograph
June 14 1999
Completion and delivery of the Entec / Mitsubishi maquila building in Reynosa. This has become Mitsubishi 's biggest and tallest manufacturing facility in North America. To take a Virtual Reality Tour of this impressive building, please click here.
       
Aerial Photo of work at  Ramirez Spec Building
June 21 1999
Aerial view of foundation and earthwork at our Ramirez Spec Building. The facility can be leased in whole or in half. 50,000 Square Foot Maquila Facility in Ramirez.
       
Overhead Crane Placement at Entec / Mitsibishi

June 28 1999
The 30 ton overhead crane was received and mounted at Entec / Mitsubishi maquila building in Reynosa. The custom built European overhead crane fit perfectly to the building's rails and ran very smoothly. Take a Virtual Tour of this impressive building.