May 1999 PROJECT NEWS | |||||
![]() |
![]() |
![]() |
![]() |
||
![]() |
May 4 1999 Enlargement of the existing office facilities at Comercial de Herramientas building in Monterrey were completed. It included A/C, carpeting, acoustic ceiling, 100 foot-candle illumination and sound insulation. |
||||
![]() |
![]() |
||||
![]() |
![]() |
![]() |
![]() |
||
![]() |
May 11 1999 Ruiz Cortinez: 55.000 sq. ft. of manufacturing and office space was completed this week. This building is located in the industrial hart of the Monterrey metropolitan area. |
||||
![]() |
![]() |
||||
![]() |
![]() |
![]() |
![]() |
||
![]() |
May 18 1999 Shipping Systems de Mexico 15,000 sq. ft. expansion was finished and delivered. This seamless expansion was achieved by the use of our exclusive of tilt wall system. Note: the shinier roof deck shows the expanded building area. |
||||
![]() |
![]() |
||||
![]() |
![]() |
![]() |
![]() |
||
|
May 25 1999 A 50,000 sq. ft. expansion at Seymour' Reynosa building has reached an 85% advance stage. This project is scheduled to be finished and delivered by the last week of June. The expansion corresponds to dark green part of the building on the aerial photograph. |
||||
![]() |
![]() |
home > may 1999 projects news